ULDC Pond 8 & Pump Station
Saratoga Springs · Utah County
- Concrete-Lined Irrigation Pond
- 17 Acre-Feet
- Location
- Saratoga Springs
- County
- Utah County
- Year
- 2019
- Owner / Engineer
- City of Saratoga Springs / Hansen, Allen & Luce
Project Overview
VanCon built a manmade, concrete-lined 17 AC-FT irrigation pond which included an inlet and spillway structures. VanCon also built a masonry pressurized irrigation pump station building to house three new 100 HP vertical turbine pumps. To manage the water, VanCon installed 2,350 linear feet of 30-inch ductile iron pipe, 1,567 linear feet of 16-inch PVC transmission pipe, and 2,390 linear feet of 24-inch RCP storm drain pipe.
Project Highlights
- 17 AC-FT concrete-lined irrigation pond
- Inlet and spillway structures
- Masonry pressurized irrigation pump station building
- Three 100 HP vertical turbine pumps
- 2,350 feet of 30-inch ductile iron pipe
- 1,567 feet of 16-inch PVC transmission pipe
- 2,390 feet of 24-inch RCP storm drain pipe
Related Projects
Syracuse Secondary Reservoir
Syracuse · Davis County · 2024
This project was bid during a period of material volatility when many budgets were unprepared for inflationary pricing. VanCon worked with the city to create alternative design engineering solutions, saving the city almost two million dollars and enabling the project to continue on schedule. VanCon excavated and poured a 37-AC-FT reservoir with underdrain to collect groundwater, installed 4,100 feet of wrapped perforated 6-inch and 220 feet of 12-inch HDPE piping to collect pond water and groundwater, and built a pump station with four 200 HP pumps. VanCon also installed 113,000 feet of 18-inch storm drain ADS, 1,700 feet of 24-inch ductile iron, 1,700 feet of 36-inch RCP, and 1,700 feet of 36-inch HDPE storm drainpipe into the road with a bore leading to the road tie-in. The project had extensive groundwater and dewatering was intensive throughout the excavation.
Secondary Reservoir
37 Acre-Feet
View Project →
Springville Bartholomew Pond and Trail
Springville · Utah County · 2014
VanCon built a 34-acre-foot regulating pond with piping for a pressure irrigation system in Springville. The project included tree removal, landscaping, site grading for a city park, grading and paving of a park trail, rehabilitation of open channels, earth dams with filters and drains, seeding, erosion control, clay pond lining, construction of concrete water control structures, open trench excavation, asphalt road and trail repair, 4,800 linear feet of 26-inch HDPE pipe, 2,000 linear feet of 18 to 36-inch gravity-flow pipe, and 400 linear feet of 36-inch C-905 pipe. Remediation of disturbed land was successful.
Regulating Pond
34 Acre-Feet
View Project →
ULDC Pond, Pump Station & Waterline
Saratoga Springs · Utah County · 2017
VanCon built a concrete-lined, 3 AC-FT irrigation pond for pressurized irrigation with a pump station housing five vertical turbine pumps (four 75 HP and one 15 HP). Piping included 1,230 linear feet of 30 and 20-inch ductile iron and 10-inch PVC pipe.
Concrete-Lined Irrigation Pond
3 Acre-Feet
View Project →
Want to Build Projects Like This?
VanCon is hiring across Utah. Join the crews building the infrastructure our communities rely on.
Join Our Team




