JVWCD Three Vault Modification
Salt Lake County · Salt Lake County
- Vault Modifications
- 4 Vaults
- Location
- Salt Lake County
- County
- Salt Lake County
- Year
- 2021
- Owner / Engineer
- Jordan Valley Water Conservancy District / Hansen, Allen & Luce
Project Overview
VanCon replaced 30-inch gate valves and butterfly valves, fittings, piping, concrete vault lids, and connections in four vaults. Self-fabrication and onsite welding were integral for this project's success.
Project Highlights
- 30-inch gate valve and butterfly valve replacement
- Fittings, piping, and concrete vault lid replacement
- Connections in four vaults
- Self-fabrication of components in VanCon shop
- Onsite welding throughout project
Related Projects
SLC East West Conveyance Line
Salt Lake City · Salt Lake County · 2022
To improve culinary water supply to the west side of Salt Lake City, VanCon installed a cast-in-place flow control valve vault and 3,300 feet of 48-inch welded steel pipe with a bore under the Jordan and Salt Lake Canal. VanCon also removed 350 feet of 8-inch sewer line, installed 58 feet of replacement sewer line, and replaced 100 feet of 4-inch waterline with a new 8-inch pipe. The pipeline also crossed a city golf course requiring coordination including installing the vault during the off season and high attention to detail in landscaping restoration. Bypass pumping was required.
48-inch Welded Steel Pipe
3,300 Linear Feet
View Project →
Woodland Hills Waterline Replacement
Woodland Hills · Utah County · 2021
VanCon helped design and then installed 21,077 feet of 8-inch PVC culinary waterline with valves and hydrants to replace a leaking waterline for the City of Woodland Hills. The waterlines were on steep slopes in a high fire hazard community with three emergency exits and narrow roads, and the schedule included winter weather. VanCon used new equipment to safely handle the slopes, kept a tight narrow work limit, and limited actively excavated areas to immediate construction to optimize access. During the CM/GC design stage of Phase 1, VanCon worked with the city budget to add an additional street to the project scope. The City later added two more streets with additional funding. Phase 1 was completed with Davis-Bacon wages.
8-inch PVC Waterline
21,077 Linear Feet
View Project →
UDOT 6200 South Aqueduct Relocation
Salt Lake County · Salt Lake · 2020
To relocate the 6200 South aqueduct, VanCon installed 1,000 linear feet of 78-inch and 2,000 linear feet of 36-inch welded steel pipe, a turn-out vault, jack and bored under Bangerter Highway, and installed 60 linear feet of 24-inch steel casing. VanCon also tied in to both 36-inch and 78-inch PCCP pipe.
Welded Steel Pipe Installed
3,000 Linear Feet
View Project →
Want to Build Projects Like This?
VanCon is hiring across Utah. Join the crews building the infrastructure our communities rely on.