Gravity Pipeline

SVSD 12200 South Sewer Realignment

Salt Lake County · Salt Lake

Sewer Main Installed
3,000 Linear Feet
Location
Salt Lake County
County
Salt Lake
Year
2015
Owner / Engineer
South Valley Sewer District / JUB Engineers
SVSD 12200 South Sewer Realignment

Project Overview

VanCon installed 3,000 linear feet of 8, 12 and 15-inch sewer main at depths from 12 to 20 feet. The job required CCTV inspection, traffic control on a UDOT highway, nine manholes, and nine laterals. The existing sewer main was abandoned.

Project Highlights

  • 3,000 feet of 8, 12, and 15-inch sewer main installed
  • Depths from 12 to 20 feet
  • Nine manholes and nine laterals installed
  • Existing sewer main abandoned
  • CCTV inspection completed
  • Traffic control on UDOT highway

Related Projects

Gravity Pipelines

Saratoga Springs Redwood Road Sewer Extension

Saratoga Springs · Utah County · 2019

VanCon used the jack and bore method to dig a 180-foot tunnel under Redwood Road and install 350 linear feet of 27-inch PVC sewer pipe. Both 48-inch and 60-inch manholes were installed. VanCon also installed 1,300 linear feet of 42-inch HOBAS sewer pipe and 800 linear feet of 42-inch PVC sewer pipe.

Jack & Bore Tunnel

180 Linear Feet

View Project →

800 South Sewer Line
Gravity Pipelines

800 South Sewer Line

Payson · Utah · 2022

Payson needed to replace and upsize a deteriorated sewer line near a new high school. VanCon installed 1,553 feet of 8-inch and 455 feet of 12-inch PVC sewer line, abandoned an existing sewer line, and installed five 60-inch diameter manholes. The streets contained complex existing utilities requiring extensive potholing. A concrete road was discovered buried in the main road during excavation. An unmarked high pressure gas line was identified due to a previous VanCon project in the area and required hand shoveling around it once it was exposed. A UDOT project was concurrent with the project creating scheduling challenges which VanCon mitigated by using the same asphalt company to reduce traffic interference by asphalting both areas at once. Groundwater required pumping throughout the project.

PVC Sewer Line Installed

2,008 Linear Feet

View Project →

Redwood Road Sewer
Gravity Pipelines

Redwood Road Sewer

Saratoga Springs · Utah · 2018

VanCon used the jack and bore method to tunnel a 42-inch, 180-linear-foot bore under Redwood Road. VanCon installed 360 feet of 27-inch, 50 feet of 30-inch and 780 feet of 42-inch PVC sewer pipe and 1,120 feet of 42-inch HOBAS pipe. Pipelines were 20 feet deep. Both 48-inch and 60-inch manholes were installed. VanCon installed culverts.

Sewer Pipe Installed

2,310 Linear Feet

View Project →

Want to Build Projects Like This?

VanCon is hiring across Utah. Join the crews building the infrastructure our communities rely on.

Join Our Team