Project Overview
To restore stability in the canyon along the roadside following a forest fire the previous year, VanCon completed channel and culvert cleaning, rock riprap bank stabilization, Gabion basket bank stabilization, a concrete diversion structure, and earthen berm construction.
Project Highlights
- Post-wildfire canyon and roadside stability restoration
- Channel and culvert cleaning
- Rock riprap bank stabilization
- Gabion basket bank stabilization
- Concrete diversion structure construction
- Earthen berm construction
Related Projects
Alpine EWP CMGC Project
Alpine · Utah County · 2013
VanCon stabilized the flood channel at three sites in Alpine City after the 2012 Quail Fire. VanCon installed riprap on channel banks, removed sediment and debris within dry stream channels, built a concrete floodwall, and did some minor demolition and repair of an existing bifurcation structure.
Post-Fire Channel Stabilization
3 Sites
View Project →
Duchesne EWP Debris Removal
Duchesne · Duchesne County · 2012
VanCon repaired and cleaned a seven-mile stretch of the Duchesne River, including removing and hauling off debris and trees out of the river channel, reshaping the banks of the river, installing embankment materials, excavating the reservoir basin, and constructing a sediment retention pond.
River Channel Restored
7 Miles