← Back to All Projects
Award-Winning Project

Achievement of Safety Excellence — Bronze

AGC of Utah 2025 Achievement of Safety Excellence — Bronze Award

Company-Wide

Man-Hours Worked in 2025
335,580
Location
Company-Wide
Year
2025
Owner / Engineer
Associated General Contractors of Utah (Chapter 46A)
Achievement of Safety Excellence — Bronze

Project Overview

Recognized by the Associated General Contractors of Utah for safety performance well below the national average. In the 2025 reporting year, VanCon logged 335,580 man-hours in the Utility Infrastructure division (250,000+ hours category) with zero lost-workday cases and zero fatalities — earning the Bronze tier of AGC's Achievement of Safety Excellence award. The company's lost-workday incidence rate of 0.00 came in well under the division average of 0.20, meeting AGC's award threshold (zero, or at least 25% below the division's overall rate).

Project Highlights

  • 335,580 man-hours worked in the 2025 reporting year
  • Zero lost-workday cases
  • Zero fatalities
  • Company lost-workday incidence rate of 0.00 vs. 0.20 division average
  • Bronze tier — Utility Infrastructure division, 250,000+ hours category
  • Below national average for safety performance

Related Projects

CUWCD Spanish Fork Provo Reservoir Canal Pipeline — Orem Reach 1B
Award

CUWCD Spanish Fork Provo Reservoir Canal Pipeline — Orem Reach 1B

Orem · Utah County · 2016

The goal of the Orem Reach 1B project was to connect a water pipeline from the Strawberry Reservoir to a concrete structure at the mouth of Provo Canyon where the Owner can choose to discharge water into the Provo River or send water via the Provo River Aqueduct to various water agencies in Utah and Salt Lake Counties. Built on solid bedrock, the concrete hydraulic structure has many large pipe penetrations and angles that made concrete construction challenging. The project included 30 to 60-inch welded steel pipe and a traffic bridge over the Provo River with a 60-inch culvert. The project was completed 30 days early.

30- to 60-inch Welded Steel Pipeline

30 Days Early

View Project →

Alpine Watershed Protection Project
Award

Alpine Watershed Protection Project

Alpine · Utah County · 2014

Originally this project consisted of installing emergency watershed protection (EWP) measures including enlarging an irrigation pond, excavating and re-grading drainage channels, installing a box culvert, rip rap, and drainage piping, constructing a concrete flood wall, and installing a permanent silt fence. After a 100-year storm caused additional erosion, VanCon secured additional NRCS funding and installed a drainage levee with rip rap. When a 150-year storm wiped out most EWP measures, VanCon crews worked through the night clearing drainage channels and digging emergency detention ponds. VanCon ultimately installed 1,850 feet of 36-inch RCP, 865 feet of 48-inch RCP, 500 feet of 60-inch RCP, and 141 feet of 84-inch RCP, with large inlet/outlet structures, catch basins, a channelizing levee with riprap, seeding, and surface restoration.

Reinforced Concrete Pipe (36- to 84-inch)

3,356 Linear Feet

View Project →

Vineyard RDA Lift Station 2
Award

Vineyard RDA Lift Station 2

Vineyard · Utah County · 2014

This lift station, awarded to VanCon by the City of Vineyard, received awards from both APWA and ACI. The station required construction of a reinforced, cast-in-place 1,239 square-foot concrete sewer lift station 32-feet deep with a CMU building. The project included liquid-applied membrane, equipment installation, 1,100 linear feet of 36-inch piping, electrical work, pumps, a 275kW Generac 600A ATS generator, a mixer, and grating with a large staircase. The VanCon team completed the project despite high ground water requiring engineered dewatering operations and trench stabilization.

1,239-Square-Foot Concrete Lift Station

32 Feet Deep

View Project →

Want to Build Projects Like This?

VanCon is hiring across Utah. Join the crews building the infrastructure our communities rely on.

Join Our Team