Park City Deer Crest Pump Station & Transmission Line
Park City · Summit County
- Vertical Turbine Pump
- 125 Horsepower
- Location
- Park City
- County
- Summit County
- Year
- 2019
- Owner / Engineer
- Park City / Aqua Engineering
Project Overview
VanCon built a 25x34-foot drinking water pump station building on a concrete pad with exterior concrete aprons, a dry stack stone veneer, and a roof access hatch. The station was connected to an existing waterline with a 12-inch ductile iron suction waterline and another existing waterline with 765 linear feet of 16-inch HDPE pipe. A water meter was installed with controlling valves. VanCon installed an air/vac station with a doghouse manhole and controlling valves. The station included a 125 HP vertical turbine pump, drain piping and a surge tank. Site electrical work was installed which included pull boxes, conduits, and pull wires. The outside landscaping included a concrete headwall and rip rap at a daylighted drain line and erosion control through revegetation.
Project Highlights
- 25x34-foot drinking water pump station building
- Dry stack stone veneer exterior finish
- 12-inch ductile iron suction waterline connection
- 765 feet of 16-inch HDPE pipe
- 125 HP vertical turbine pump
- Air/vac station with doghouse manhole
- Water meter and controlling valves
- Surge tank installation
- Full site electrical — pull boxes, conduits, pull wires
- Concrete headwall, rip rap, and revegetation
Related Projects
Sandy High Bench Booster Station
Sandy · Salt Lake · 2012
VanCon built a 43×40-foot pump station with welded steel manifolds, three 350 HP vertical turbine pumps, piping, storm drain, electrical equipment, grating, stairs, site improvements, and landscaping.
Pump Station Building
43 × 40 Feet
View Project →
Salt Lake City Capitol Hill Pump Station
Salt Lake City · Salt Lake County · 2014
VanCon installed a new pump station with three 200 HP vertical turbine pumps, a hydro-pneumatics surge tank, an overhead bridge crane, steel piping, valves, metering, a backup power generator, SCADA, instrumentation, and controls. In addition to the station, VanCon installed 5,000 linear feet of 12-inch culinary ductile iron pipe, four air valve vaults with isolation valves, drains, twelve buried gate valves, connections to existing piping, and made modifications to an existing tank drain. The project required traffic control, landscaping and irrigation, plantings, stormwater detention, reseeding, concrete, curb, gutter, asphalt, surface restoration, and various pump station and pipeline appurtenances.
Vertical Turbine Pumps
3 x 200 Horsepower
View Project →
950 North Sewer Lift Station & Maintenance Building
Utah County · Utah County · 2024
VanCon constructed a new sewer lift station and maintenance building at 950 North, including all civil, mechanical, and electrical site infrastructure required for long-term pump station operations.
Lift Station & Maintenance Building
2 Structures
View Project →